West of Duddon Offshore Wind Farm
​2010-2012​Tender, Planning and Design
2010-2012Geotechnical investigations
May 2013 Offshore Substation Installation
May-November 2013Foundation Installations
March-October 2013Export Cable Installations
June 2013-March 2014Array Cable Installations
August 2013-Summer 2014Installation of Turbines
August 2013-End 2014Turbine Commissioning
​October 2014​Full power achieved
​October 2014​Inauguration